Works Information – A2 Jubilee Way

A2 Jubilee Way – Investigations

I am writing to advise that A-one+ on behalf of Highways England will be carrying out ground investigations and surveys of the crash barriers. The purpose of these investigations is to highlight if there is a need for future barrier repairs and resurfacing at this location.

In order to carry out these works as efficiently and as safely as possible, work will be undertaken whilst we facilitate full overnight closures of the coast bound carriageway on the A2.

 

Series of full closures on main carriageway

Dates and timings

A2 Jubilee Way to Docks Roundabout

16 October to 18 October 2017 for 3 shifts.

8pm to 6am

During the works, we will be closing the dedicated lane from the port which leads Southbound up Jubilee way.  Access will still be granted from the roundabout.

 

Diversions- A clearly signed diversion will be in place during all closures utilising local routes, suitable for all types of vehicles when full closures of the carriageway are in place via Whitfield Hill to York Street.

Diversion route for coast bound traffic is via the A256 to join the A20 at Woolcoomber/Townwall Street.

If you have any questions or if you’d like to know about the work taking place, please do not hesitate to contact us.

Phone: 01732 446800

Post: 10, Kings Hill Avenue,

Kings Hill,

Kent

ME19 4AR

Email: area4enquiries@aone.uk.com

info@highwaysengland.co.uk

Web: www.highways.gov.uk

 

Please be aware that these works have been carefully programmed but are subject to change due to weather conditions or unforeseen circumstances

 

Kind regards,

______________________________________________________________________
Highways England Ltd
Bridge House, 1 Walnut Tree Close, Guildford, Surrey, GU1 4LZ
Tel: 0300 123 5000 Email: info@highwaysengland.co.uk
www.highways.gov.uk